Summary of the ECA Board Meeting January 26, 2016

Board Present: Sharon Bobb, Patricia Batey, Clifford Cohen, Peg Downey, Jim Jones, John McNerney, Steven Schattman

Others Present: ECA General Manager Terry Lee, ECA Assistant General Manager Wanda Powell, ECA Legal Counsel Jeremy Tucker, WJE representative Ken Kosteva

President’s Report:
—Board is considering the recommendation of the Budget & Finance Committee for an auditor to do the Transition audit.  A selection is anticipated shortly.
—Two thefts in the Elizabeth garage as well as two others in the Willoughby. Advice is to report all thefts and avoid leaving valuables in your vehicle.
—Appointment of nominating committee: Jerry Feldman, Tobi Esler, Jeffrey Axlerad (Chair)

Comments from the floor:
—Pam Dillon raised question about whether the Bylaw Amendment regarding reducing the percentage vote of the Association down to 66 and 2/3 was registered in the Montgomery County Courthouse and when could owners expect to get a copy of that document so that individual owner documents could be up to date. Jeremy Tucker said that the amendment had been recorded and was available online. Although the Association is not obligated to provide copies, he would arrange to have copies at the Concierge Desk.

—Rita Miller said the dome over the pool is leaking and wants to know when that will be fixed. She also said one of the swimmers was bringing her dog to the pool and the dog was urinating on the pool deck. Sharon Bobb asked Wanda Powell to identify the dog and take appropriate action.

—Linda Kontnier asked for monthly updates on the land development issue that impacts our block in Friendship Heights. Peg Downey, our representative to the Council, agreed to keep the Association informed.

—Pam Dillon asked for an update on the FY 2015 audit report, which is late. Tucker said that the Association was doing everything in its power to ensure that the required data from Legum & Norman would be made available to the auditor so that the audit could be completed.

—A status on the new leak that occurred on the 18th floor East. Answer, provided by Terry Lee: cause was snow and ice on the grate located on the roof. Problem being attended to.

—Mary Catherine Curran asked about whether the canopy replacement project would also address the cracks seen on the lower level walls (West side) at the front door and replacement of the air-leading front doors.

—Karen Hendricks asked whether the old fire pump works since rumors abounded that it did not. Terry Lee said the fire pump passed fire department inspection every year. Questions related to the fire pump replacement were: will the shut down on Jan 29 effect water (as well as electricity). Answer: Yes, it could. How would people get into the garage after the electrical power is shut down. Sharon Bobb asked Terry Lee if he could hire security guards to be stationed at the entrances/exits from the garage by hiring security guards at those locations. He responded that he could. 

—Karren Alenier asked for assistance from outside engineering companies to look into a building-wide problem that causes excessive heat in some apartments when their individual HVAC units are not on. Additionally the four pipe system is not working which means there is no air conditioning.

—Molly Franz had numerous questions.  She was reminded the purpose of the monthly Board meeting is to conduct the business of the Association. In order for meetings to proceed in a timely manner, and not go until midnight, the Board has asked residents to limit their comments to 3 minutes (a common practice for condominiums), and respectfully requests that comments be limited to the topics on the agenda.  In order to provide an open forum for residents to air their concerns with the Board, but without regard to topic or length of time they wished to speak, the Board introduced “Conversations with the Board” several months ago.  The meetings were suspended due to holiday activities and the press of business, but Cliff Cohen announced they would begin again soon.  Frantz objected and said the reason most people come to the meeting is to address problems that have not been taken care by management.


Treasurer’s Report:

McNerny said the ECA reserve account was deliberately kept low to avoid borrowing too much money. However, he said the line of credit substitutes for the reserve.

Question from the Floor on High Gas Cost:
—Pam Dillon asked why the expenditure for gas was $16,000, which is more than current costs although that figure occurred during an abnormally warm period. Answer: Teri Lee said the figure was an accrual estimate and not actual but the next report should reflect actual costs. Jeremy Tucker said the Finance Report is for the Association Board and not up for detailed discussion by members of the Association.

Committee Reports:
FINANCE
The Finance Committee interviewed two auditors referred by Counsel for our consideration and made a recommendation to the Board.

DESIGN
The next meeting with Phyllis Hartman will take place Feb 8 at 4 pm.

LANDSCAPE
Ruppert, our current landscaper which has not been satisfactory, has merged with the largest landscaping company in the area so this will be taken into consideration in deciding who will address our needs.

CONVERSATIONS WITH THE BOARD
Audience members want this committee to resume its service. Cliff Cohen asked if Mondays at 6 pm might be a better time for Association members. He said he would schedule a meeting soon on a Monday night.

Old Business

Canopy Replacement: Ken Kosteva presented two design concepts for a new canopy. These are not THE designs he is recommending. They are just two concepts to give us an idea of what sort of change a new canopy would make to our building. He pointed out that the current canopy is leaking and must be repaired. Moreover, it does not completely shield people from rain and snow when they board the bus. A new canopy would solve those problems, and would improve the overall appearance of the building.   Questions were asked about when this would take place since it was in the budget for 2017 or 2018. Some Association members were against starting the design phase without implementation being close to that product production. Ms. Bobb suggested that the canopy replacement project by addressed by the new management team, scheduled to take over on February 1.

New Business

A motion to authorize Densel to conduct asbestos testing of insulation around heating supply line on the 18th floor was passed.

A motion to approve a second smoking questionnaire was passed.