Present: Judi Barth, Charles Bressler, Ilo-Mai Harding, Alexandra Kielty, Alfred Muller, David Robinson, Jim Santos, Greg Roby, recording secretary
Absent: Seth Levine
Treasurer's Report:
Issues with L&N financial reports that are being worked on.
Capital Improvement Program:
The name is not accurate according to Ted Ariev. New name is Maintenance, Repair & Replacement Program.
Per approval by the ECA board in December, Mendoza, Ribas, Farinas & Associates has started work to analyze mechanical, electrical, and plumbing systems. Mid-spring report expected.
Structural firms interviewed (3 out of 4 provided proposals) most have already worked in the Elizabeth. We are ready to make a contract. Structural engineers will look at the roof (including mechanical equipment supports), façade and plaza, window and doors, balconies, garage, and interior survey.
Architectural services got proposals from two of three. Prequalifying only. No project specs and certainly no contract at this time.
Three Environmental consultants contacted and interviewed. No contract at this time.
Corridors, canopies, swimming pool, exercise rooms, fire alarm systems, communications & security systems, manager's office -- all of these areas need to be addressed still.
Want an in depth study to ensure quality work. The preference is to work with contractors who have experience in our building.
MOTION: approved Wiss Janney Elstner Assoc., Inc. as structural consultants.
Guidelines for hiring contractors by owners.
The Board accepted and discussed the guidelines for hiring contractors by ECA unit owners. ECA legal counsel Jason Fisher prepared the document accepted and it includes comments from ECA members. The resolution package includes changes to the ECA House Rules but it does not change the hours a contractor may work in our building. A side note is that if a unit does not comply with these rules, ECA management will send a notice of violation to that unit owner. The unit owner will then be summoned to a closed door meeting with the ECA board to hear the unit owner. If the violation stands, the unit owner would be fined.
MOTION: to accept resolution passes but did not extend work hours beyond 5 pm.
Pool management:
pool aerobics with AquaFit pending so that they can supply liability coverage, but we will get a new pool management company—Winkler. Fee structure would be the same for the aerobic class. Winkler starts Feb 1. There will be regular oversight to ensure good service.
Elevator repair status.
Work began on the East side with car #5. That work should be completed no later than Monday January 30, 2012. Next will be East side car #6. After that work will start on West side elevators one at a time. The work includes modifying rollers and tracks on every floor. Another part of this project is to replace the hoist way motors. This will result in more efficient elevators and a savings in 2012 of $30,000.
Complete Building Service now working harder than they expected. Santos says expect a renegotiated contract (more expensive) with CBS this summer.
Roby thanks board for patience on L&N accounting software. November statement was provided for this meeting. The problems with the software change did not effect payment of any ECA bills.
Roby is working with ECA counsel Jason Fisher to see if we can avoid a bylaw amendment related to issues in replacing fan coil units throughout the building. He expects an answer within 10 days.
Santos discussed $4100 cost to replace a sliding glass door. Interior repairs to water damaged floors can cost $800 to $2000. These repairs cannot wait until we do building-wide replacement of doors & windows.
Pest control is not providing adequate service. Santos recommended Erlich Pest Control, which will give us an increased level of service at a lower coast.
MOTION: approved new pest control provider.
Need no smoking sign on patio. Santos will install two signs out in the patio area, similar to the ones on the swimming terrace.
Report on hallway renovation. Custom carpet can be replaced down the road & it is more durable. Two options for furniture.
Comments from Floor
Concerns about spending money on projects involving health and safety first. Before we spend money on hallway renovation.
Suggestion about having attorney present. Answer was professional management should take up the slack. Greg Roby has law degree.
Doors & windows still seem to be the top priority. It would make sense to move forward with door and window replacement now instead of making these emergency repairs that may not match the future replacements.
Security in building is lax. Not getting calls about visitors. Front desk does not seem able to monitor who is allowed to go through the lobby. Residents are observing workman with equipment and residents with bicycles going though the font doors and across he lobby. Bikes are suppose to be taken out through the garage.