Present: Directors: Ted Ariev, Ilo-Mai
Harding, John McNerney, David Robinson, Steven Schattman, Herman
Stekler, ECA General Manager Jim Santos, Legum & Norman Regional
Manager Robert Craig, recording secretary.
Absent: Charles Bressler
Highlights of the meeting:
President’s Report.
--Awaiting Fire Marshall signature on new fire protection.
--Cleaning of exhaust ventilation from dryers and exhaust fans
will take place. (This is done every 12-15 years. Project will take 160 days to
complete after the contract begins.)
--Status report chart will be (and are) posted in the elevator
lobbies of our two towers.
--ECA Board member candidates search now underway. May 1 is the annual meeting where 3 board members will be elected.
Treasurer’s Report.
--Five accounts in collection (one in bankruptcy)
--Bank borrowing will begin this summer.
--Alternate financing may not include prepayment of condo fee
but there is still the possibility of owners buying into the project in a kind
of bond like arrangement.
--An alternative financing survey form has been send with call
for candidates to the ECA board.
Report from Ken Kosteva of Wiss Janney.
--Will mount roof anchors to allow scaffolding for window
washing and the window/balcony door replacement project.
--Balcony restoration will be done consistent throughout the towers. (Every balcony will be upgraded.) It is
noisy work.
--Repair takes about one week but residents can live in the
apartment while the work is being done.
--Possibility of floor to ceiling windows to replace current
look. This stirred up considerable controversy. Some of the issues include the
need to replace window treatments, liability issues for children, built-ins at
the current window.
--There are over 800 windows.
--There is sufficient insurance coverage for damage to
individual units.
--Project will take one year.
--Double pane windows will have significant thermal value.
Storage Committee.
--Storage includes items belonging to former and dead residents.
--Some items are illegally stored (like furniture, empty boxes,
paint.
--Storage needs to be tracked with computer software, not
currently part of the process.
Canopies.
--This stirred up some controversy about which canopies were
needed and whether it made good financial sense to repair what would remain. (Remove
West garage canopy but keep East garage canopy over the steps.
--The lobby canopy will not be replaced until 2019 by the
current plan.